on 08-20-2007 4:20 PM
Hi experts,
When we run MRP for a material that needs to be stock we run MD02 with the following parameters:
Processing key NETCH
Create purchase req. 1
Schedule lines 3
Create MRP list 1
Planning mode 1
Scheduling 1
We got a Purchase Requisition... that is what we want.
BUT
If we run program RMMRP000 with the same parameters than above with Planning day = Todays' date, we got a Planned Order
We do not want Planned orders but requisitions.
I put a check in the two user exits I found:
ZXM61U01 and 02, but the system does not stop there.
Can some one explain me the differences why I am getting planned orders?
Thank you.
Monica.
I found note 23922. Solved it.
MRP group was configured for Planned orders. Some materials had it in the material master.
Writting this in case someone needs it.
Monica.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you try with purchase requisition in opening period option ?
Regards,
Senthilkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.