contract case

hi all

i hav raised one contract of Rs. 10000 on vendor....

and vendor completed the work of Rs2000

and now i hav to move rest of the work on other vendor ....

how to map ths scenario in sap

sapmm

Former Member
Former Member replied

Hi

Raise a new contract for new vendor with target value 8000. Change the old vendor's contract by giving the latest date as validity end.

regards

Chetan.J