Production Order settlement to Sale Order

Hi Gurus,

I have crated a sale order through VA01, I crated sale order specific BOM through CS61 and after that I executed Cost Estimate for the sale order.

Sale Order No: 260

Finished Product : 610

Semi Finished: 611

Semi Finished: 612

I executed MRP for sale order 260, System has created planned production for Material 610,611 and 612.

When I am trying to convert the planned production order to production order, system is automatically picking up settlement rule as Material instead of sale order for all the production orders. System is not allowing to change the settlement rule manually.

Our requirement is, Production Order of SFGs(611 and 612) should be settle to Production order of Finished Product(610). and the total cost of the production order of Finished Product(610) should be settle to Sale Order (260).

How can I get the above settlement rule into my production orders as default.

Please help me in this regards and guide me if i am going in wrong way.

Thanks in Advance

Ganesh

Note:

1. Our scenario is Make-To-Order.

2. I am using same Order Type for all the production orders.