cancel
Showing results for 
Search instead for 
Did you mean: 

No PGI Scenario

Former Member
0 Kudos

Hi,

In which scnerio we don't do PGI in sales process.

Regards

Prabudh

Accepted Solutions (0)

Answers (7)

Answers (7)

Former Member
0 Kudos

Hi Prabhudh,

PGI is not required in the following cases :

1. Credit memo request

2. Debit memo request

3. Service Items

Reward if helpful.

Regards

Priyanka Dixit

Former Member
0 Kudos

Dear Prabudh,

generally the delivery process can be finished without posting the goods issue, if you deliver non-stock materials: for example, you deliver services. In this case you should confirm service only and there is no movement of goods.

I hope, this info helps you a little bit further.

Kind regards,

Akmal Vakhidov

Development Support SD, SAP, Walldorf/Germany

Former Member
0 Kudos

Credit Note, Debit Note, Transfer Posting in MIGO / MB1c etc,.

Do you have any specific requirement ?

Thanks,

Ramesh

Former Member
0 Kudos

hi ,

we can use pgr instread of pgi in consignment process, in debit memoms & credit memos,ther ewill no pgi scenario.

Former Member
0 Kudos

Hi Prabhudh,

When we use

Credit memo request

Debit memo request

Consignment Issue in the consignment process

Service Items

PGI is not required.

Regards,

Ravikiran Pochiraju

Former Member
0 Kudos

Consignment Issue has PGI, that results in reduction in customer's consignment stock and plant stock. In Consignment fillup we do PGI. Consignment pick up and consignment Returns sill have PGR.

Former Member
0 Kudos

Credit Memo & Debit Memo

Invoice correction

Former Member
0 Kudos

Service related products like DIEN ITEMS

Former Member
0 Kudos

Transfer order from one storage location to another MB1C or MB1B.

Credit Memo & Debit Memo

Reward if useful.