S_ALR_87013326 - Profit Center Group: Plan/Actual/Variance

Hi,

I am looking to branch off from a line item in the S_ALR_87013326 - Profit Center Group: Plan/Actual/Variance report to the actual posting document. Is there a way to do this?

Thanks,

Ram

Message was edited by:

Ram R

Former Member
Former Member replied

Yes Ram it is possible to drill down. First execute the report > select the balance you need to drill down > go to "Call up reports" icon on top > then select Profir centre : Actual line items

Hope this helps.

Regards

Nadini

0 View this answer in context