Former Member
0 Kudos

While using cap evaluation in planned order, I checked the profile used. (Extra -> Display total profile) . It is SAPMPSG001, Now I want to use another profile.

Where is this setting?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sandeep,

do the settings in OPD0 and assign it in OPJK

Make sure you do checked for capacity reqmt in OPU3 and OPU5

Thanks

Bala

Former Member
0 Kudos

Dear Bala,

Overall profile in Cap. evaluation (Planned oredr stage) is different than specified in OPJK.

Please check it again.

Former Member
0 Kudos

Hi Sandeep,

Please assign the overall profile in production scheduler profile OPKP.

Regards

Ranga

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi sandip,

Go to OPA6, Select whichever profile suitable to your requirement.

Reward if Useful.