on 08-18-2007 9:10 AM
In Product costing
For purchased materials I would like to use last purchase order price.
For subcontracted materials
We have multiple vendors doing same processing on same material at different rates. But for costing purpose I would like to take the highest price available in inforecord.
Can anybody suggest me a way to do this. particularly the subcontract point.
thanks in advance.
Hi
In the strategy sequences you hv an option " Valuation price with user exit". Check whether this works for you and gives you choices as u desired for both material valuation and sub contracting
If the above does not work let me know - Iam thinking of other option to meet the requirement
Please assign points and gud luck
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.