Hi all,

I am scheduling the report in Background, I know it will take 3 hours.

I want to change the program, then

is JOb will get Cancelled or not?

regards,

Ajay reddy

1 ACCEPTED SOLUTION

Former Member
0 Kudos

if in the definition of the job there is name of the AbAP PROGRAM, it will automatically take the latest active version. no the job won;t get cancelled.

A.

5 REPLIES 5

Former Member
0 Kudos

Hi,

After you scheduled the program it will be running even if you change the program.

Job will not be cancelled.

Reward if helpful.

Former Member
0 Kudos

if in the definition of the job there is name of the AbAP PROGRAM, it will automatically take the latest active version. no the job won;t get cancelled.

A.

Former Member
0 Kudos

If you change the report while job s running it will not get affected because before running the job, it will buffer a copy into memory and access that copy only.

Former Member
0 Kudos

If the job is already started then it is not effected by the change

Former Member
0 Kudos

hai Ajay,

once if u Schedule a job in Background it will be Processed Until

you cancel or kill the job , if u make any changes in your Report

you want to Schedule the job once again....