HI Sap gurus,
I am trying to post Billing doc to accounting and getting following error.
Valuation with material cost estimate: error with product "DPSS_SEQ_01"
Message no. KE 350
Diagnosis
In Profitability Analysis (CO-PA), the system tried to valuate a line item using the current standard cost estimate.
In order to determine the current plan period, the system needs to read the valuation segment of the material master.
The system has found that the current plan period is not filled forproduct "DPSS_SEQ_01" in plant "LA02".
Display material (View: Costing)
The system looked for the material cost estimate using costing key "ZDA", as defined in the Customizing settings for CO-PA.
System Response
The document cannot be processed.
Regards
shekhar,
Hi run the costing T-code CK11n and release it through ck24 it will update costing and rlease the billing document.
Best Regards
Sainath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In material Master record in Costing2 view maintain the Planned price1 and standard price.
regards,
v.s.vas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.