on 08-16-2007 6:46 PM
Hi - any thoughts greatly appreciated
We are using RRB via projects/WBS linked to activity types. Activity types linked to material masters within the DIP profile.
SD contracts created and assigned to WBS,
SD Pricing created at the SD document type/material level and assigned to pricing procedure which is assigned to both the contract document type and the RRB debit memo request
ESS posts time
When running DP91 no sales condition is found. When I simulate the DMR and analysis pricing it does not find the condition records, because at that stahe the DMR document number is not available! However, I think this should pull through the SD contract document number
Any thoughts?
Steve
Thanks
Hi Steve,
I'm currnently working on a similar concept. I'm sorry to say but can you be more specific on your requirement...............
Thanks
Sai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi.
OK I will try and explain the issue
I have an SD contract type (ZCC) copy of standard document type (WV). Have also created a copy of standard Debit memo request (ZSDR) from (DR).
Have created three new pricing condition tables
901 - Uses sales document, sales document item
902 - Uses customer, material
903 - Uses material
Assigned these condition tables to a new access sequence, which I have then assigned to a pricing condition record, which is also included in the pricing procedure
The pricing procedure is then assigned to both the SD contract (category V) and the SD standard order (category A)
I create condition records VK11 for my SD contract, item and material, I book time against the appropriate WBS/SD contract and run DP91. When I simulate the Debit memo request then no pricing condirtion is found
However, if I create VK11 for the next level down (Customer and material) and rerun the DP91 then this second level pricing is found)
Any ideas why it does not find the first record...it looks like it is trying to use the document of the ZSDR debit memo request (which has not been created yet). When it should be using the SD contract assigned in DP91
Regards
Steve
Hi Steve,
can you explain it more clearly, maybe i will be able to help on this.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
You may get info on
http://help.sap.com/saphelp_47x200/helpdata/en/cb/1bad3cf7ca0855e10000000a114084/content.htm
Vrajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.