on 08-16-2007 5:02 PM
Hi,
We have 0IC_C03 and it is getting populated with 2 data sources BX and BF
from last 2 years,
Now we have decided to take UM also, how do we go abt it ? what will happen
if i load UM data to cube as on date and do collapse - marker update(as it
is mandatory) ?
Thanks,
Vijay
Vijay,
You should do with UM the same you did with BF.
Use as reference the date you used for BX initialization. Load historical data and compress with "No Marker Update" set. Then the initialization and "normal" deltas, the same as BF, with "No Marker Update" not set... Should be fine.
Anyway, test it before moving it to Prod...
Good luck!
Luis