on 08-16-2007 3:28 PM
Hi,
We set up SRM SWCV in Central SLD and using that in Dev system.
We want to transport this SWCV from Dev to QA using CMS.When we are trying to do this transport we are getting error and the reason is there is no entry of SRM stuff in CMS.
Our CMS is pointing to Central SLD and when we are trying to Update CMS it is pulling all other SWCV s from Central SLD except SRM stuff..So we couldn't add SRM SWCV in CMS...
So,please let us know what we are doing wrong...or Should we approach differently to load SRM content in QA systems..
Thanks in advance
Venu
Yes Venu,
You need to import SRM Content into QA syste.
DO NOT TRANSPORT CONTENTS....!
Thanks