Deactive Year dependent master data (Funds center)

Former Member
0 Kudos

Hi community!

I've create Fund center as year dependent in V_FM01_M estructure. Really i don't need it.

Anyone knows if exist any function module or action to be done, in order to deactive Fund center as year dependent master data?

Thanks an advance

Best regards

2 REPLIES 2

joseluis_basalo
Advisor
Advisor
0 Kudos

Hi,

As far as i know thisis not possible. Documentation in program RFFMMDACT indicate it.

You use the program RFFMMDACT to execute the activation of master data

maintenance to year dependency for an FM area.

You can decide here if only funds centers or only commitment items or

both master data categories are to be activated.

Note that you can no longer cancel year-dependence once it has been

activated.

******

Maybe with a own program, but i don´t now anyone.

Regards, JLB

Former Member
0 Kudos

Hi Dolors,

I confirm JLB it is impossible to go back to year independant master data. Please create anothe dev sytem to do your customizing.

We had this problem during prototyping FM and we were obliged to have another development system (sap confirmed) because we wanted to activate annual budget along with multiannual budget which requires year independant master data.

I hope you have your definitive response here evan you have to go back in your customizing. I hope you are still in development

Best regards

salvator

Senior PSM-FM Consultant

Lausanne, Suisse