on 08-15-2007 11:37 AM
Dear All,
When we assign a Equipment PRT in maintenance order, it can not check the availability of the equipment PRT, only shows that the PRT is available although the same PRT is assigned to another maintenance order with same required dates. So is there any way that we can restrict the availability of equipment PRT once assigned to a maintenance order on a particular time.
Thanks in Advance
Jadoon
Thank you for the reply.
If for example, that was the case than why in prt dates, we give the PRT usage dates and duration ....
Any helpful answer would be highly appreciated.
Regards,
Imran Afzal Khan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi imran,
it is used for measuring usage of PRT .say for example if you are using a CRANE as PRT then as you use it, it becomes wear and tear.so inorder to capture the usage times it is specified in order. in PRT master record if you specifiy at which counter reading you have to restore the PRT then based on this counter reading and you confirm the PRT usage, a maitnenance order will be generated.
i hope this will clear
thyagarajan
yep I have the same problems with PRTs it is really unbelievable that you cannot schedule PRTs as you would expect from such feature to do.
I have the same requirement where I want to schedule a prt for a certain period so you should not be able to schedule it again in the same period but should be ablt to schedule in other periods.
Dear Thyagarajan,
In cutomizing all the rules are checked in availabilty check of PRT but when i take a scenario of creating two maintenance orders on an equipment on the same date, same operation time and select the same PRT then the system cannot perform the availability check of PRT only give a message that PRTs are available.
Is there any other setting that i have to maintain ...... It would be every helpful if u can take the same scenario and check availability of PRT as an equipment and let me know .....
Thanks for you help.
Regards,
Jadoon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi imran
prt availabiltiy check is only for checking whether PRT is available or not( ie if equipmnet status is allowing or not and in case of material whether is available .if one material is there, you can use the same one for different orders,
Using PRTs for which you have created equipment master records in the system, has the following advantages:
You can monitor wear and tear of production resources/tools.
To do this, create a counter for the PRTs equipment master record (PRT usage counter). The counter reading, which is updated when the order is completed, provides information about how many units are available after the PRT has been used.
You can restore the production resource/tool to working condition in a cycle.
You also define a preventive maintenance plan for a PRT, in addition to a performance-based counter. In the preventive maintenance plan, you define at what counter reading (meaning at what level of wear and tear) the PRT must be restored to working order. You enter the preventive maintenance plan in the PRTs equipment master record.
It will not check whether the same prt is used in different work orders
regards
k.thyagarajan
hi imran
kindly customize in Plant maintenance>maintenance and service order>functions and settings of order type>availablity check for material ,PRT and capacity.
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Imran,
I have same problem with PRT in PS. Please share with me solution.
Regards
Suhel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.