on 08-14-2007 9:32 PM
Gurus,
I am looking for the attribute which corresponds to the task's 'Percent Complete' field. I intend creating an Evaluation Layout with 'Percent Complete' as one of the columns. Just not able to find out.
Please suggest.
Thanks and Regards.
Hi Bittu,
The 'work_complete' may fullfill your requirement, which is defined as
sum. actual work / ( sum.rem.work + sum.actual work)
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Zhenbo,
Thanks for responding.
I did try 'Work Complete'. I have a scenario wherein, for a task, the 'Work' is 50 hrs. 'Confirmed' is 25 hrs. 'Remaining Work' is 25 hrs. By this, I should get 50% as the 'Work Complete'. I get 0 in Evaluations.
There's another field 'Percent Complete'. This is what I was looking for. I inentded rolling up the values for each task in a phase to the phase and finnaly to the project. But having not found the 'percent Complete' for the task, I am not able to proceed.
Thanks and Regards.
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.