Where can we configure the start day of the week (e.g., Monday or Sunday). When we release DP to SNP, order category FA=FC Reqs are falling on Monday. I am being asked where this is set at we have seen disturbing results where some location-producta have FC Reqs on Monday and some Sunday. We are trying to determine if there is some sort of bug in SCM 5 as in APO4.0 all FC Reqs fell on a Monday at time= 00:00:00

Message was edited by:

Dan Spieth

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member184627
Active Contributor
0 Kudos

Hi,

You can use planning calendar (T.code md25) to define the start of the day Eg:mon/tue/wed etc.