SPP - Problems in realignment of demand history

Former Member
0 Kudos

Hi

We are trying to adjust the demand history of a product but we are getting this error

<i>"Error Locking Unlocking. (Close) realtime data load (DS 9ADEMCRT, QS SCT001, DTA 9ADEMCRT) not started."</i>

It seems there is some kind of delta queue and daemon needs to be created.

Anybody having any idea on this ?

Thanks and Best Regds

Mitesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

The Problem got resolved after looking at the SAP note on real time data load in SPP.

Former Member
0 Kudos

hi Mitesh

We do have an issue in setting the daemon can u pl share the note

Former Member
Former Member
0 Kudos

Hi Mitesh

Thanks for reply

But we are in 7.0,

can we go ahead with Note 918444..

regards

SRS Kannan

Former Member
0 Kudos

Hi Kannan,

We are also facing the same issue for SCM 7.0.

Are you able to resolve it using note 918444??

Regards,

Mahendra

Answers (1)

Answers (1)

Former Member
0 Kudos

The issue got resolved for SCM 7.

We found that the RFC settings in SCM system, for SCM client, were wrongly maintained.

Former Member
0 Kudos

Hello Mahendra Kumar - We are facing the same issue and we already checked our RFC connection and it is correct but the error is still occurring. Is there anything else that we need to check or do to rectify this issue?

Thanks in advance!