Hi,

I need some advice for the following scenario.

That is to PGI a delivery with the “Actual GI date” for a particular month (July) but the PGI was reversed for the following month (August) where the original PGI had been done for the correct month (July).

when we try to PGI again we get stock deficit errors.

Please explain the process to follow if such scenario arises.

Thanks

Keshi

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please check the below scenario.

IPGI'd on the the 13.09.2007.

Reversed PGI on 05.10.2007

Then when we tried to PGI on 13.09.2007, it gave the error "Deficit of BA Unrestr. prev. 100 PC : 70001358 "

So as u'll have suggested again issued the goods on the 05.10.2007.

But now when we try to reverse PGi on the 13.09.2007, it gives the error message " Cancellation date 13.09.2007 is before the goods issue date 05.10.2007"

Appreciate your feedback on this. I want to carry out the PGi on the 13.09.2007.

Thanks

Keshi

Manoj_Mahajan78
Active Contributor
0 Kudos

Keshini,

You have Reversed PGI on 05.10.2007...At the time of revesing PGI System taken current date as default..but you can change it as per your reqt..Now as you have already issued goods on 05.10.2007 how can you reverse it on 13.09.2007 which is in the past..

Like if you have issued goods today...You can reverse it today...And not yesterday...

No..I think you cannot do it...you have to try with date 05.10.2007 only..

Go to VL02 SCREEN (YOUR INITIAL DELIVERY)...Go to Environment...view material document there see all updation would have happened...

Reward if U FINDS THIS AS USEFUL...

Regds

MM

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

In PGI cancel pl. check where the stocks are moved and correspondingly u need to get them into unrestricted use to do PGI again.

Regards

Mahesh

Former Member
0 Kudos

Dear Keshi ,

for the reversed pgi, now you can do a pgi on same date as reversed and then reverse the pgi on the required date

please note that when reversing the pgi by default it takes current date, change that to the required date and save.

hope its useful

Regards

Krishna

Former Member
0 Kudos

This is beacuse You hv done the PGI reversal in August. That means your stock has come back only in August & not in July.So you hv to post the new PGI only in August.