Hi all,
Please let me know to download Budget data for WBS elements what are all the reports available in standard SAP PS.
Regards
Tushar
Dear Tushar,
these are some of the standard reports in SAP on budgets.
Please go through them.
Funds Overview S_ALR_87013556
Budget/Actual/variance S_ALR_87013557
Budget/Actual/Commitment/Rem Plan/Assigned S_ALR_87013558
Budget/Distributed/Plan/Distributed S_ALR_87013559
Budget Updates S_ALR_87013560
Availability Control S_ALR_87013561
Budget/Actual/Variance S_ALR_87013583
Budget/Actual/Commitment S_ALR_87013584
thanks & regards
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Transaction CJE0 will give you list of SAP reports. Select suitable report from there.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.