We are implementing SRM -EXtended Classic Scenario.

The PO is created in SRM and a copy is sent back to ECC. Therefore PO is avialable in both the SRM & ECC systems to be pulled into BI. In BI we have serperate content available for Procurement Analysis in ECC(based on LO cockpit) and SRM area. (under 0SRM & 0SCM). The contents /data model look very different.

Any benefits/pitfalls in using either of the business content for SRM procurement reporting?

Accepted Solutions (0)

Answers (1)

Answers (1)

yann_bouillut
Active Contributor
0 Kudos

Hi,

As ECC contains both SRM and non SRM PO, i will suggest to do the reporting by extracting ECC values.

This will enable the reporting merge of both worlds.

Kind regards,

Yann