cancel
Showing results for 
Search instead for 
Did you mean: 

Issue- matl staging date 30.07.07 replaced by current date

Former Member
0 Kudos

Dear Friends,

Please let me know why these 3 errors are being shown while doing delivery. But sotck is available, I have checked in MB5B,MMBE also.

Item 000010, matl staging date 30.07.07 replaced by current date.

Only 0 TO of material xxxxxxxxxxx available

An item with no delivery quantity is not permitted. Item will be deleted.

Message was edited by:

Sreehari Kondapalli

Message was edited by:

Sreehari Kondapalli

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Use the T.code MMPV and update current date for your company code and post delivery or GRN.

every month we have close the pervious month and open the new month which is taken care of Finance consultants.

Reward if it helps

Regards

Prasanna R

Former Member
0 Kudos

Hi Prasanna,

Already the closing of posting perion was done, in the material master also it is showing that current period 05-2008.

It could be some other reason.

Thanks & Regards,

Sreehari