Is there any table in SD, that holds the delivery dates requested by the customer or the earliest date that the system can propose to the customer.
This is under the column "First date" in the Sales Order item details.
Rgds,
Pr
Pls check VBEP and VBEH which are related to schedule lines and schedule line history.
VBEP
Fields can be RSDAT
VBEH field VDATU
You can also check VBKD-EDATU
Reward if this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry, what i mean to say is,
If the commit date has changed to a new date & again changed to a re-scheduled date, where does these dates get saved in SAP table.
Rgds,
Pr
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.