Can Anybody answer me Even after a Inspection plan is there why is this status coming in my inspection lot.

Second one how do I release it??

Regards

Suresh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

I found the answer. If you lready have a InsPLan Then go to QA02 enter the Ins.Lot Then goto ins.Charac. in the lot assign the task list to it. Here the inspection plan gets assigned to the lot.

Or

Create a new Insp.Plan which is pre dated to the inspection lot. then follow the steps as above.

Former Member
0 Kudos

HI,

I think you have assigned inpsection plan to the material in the past date i mean after the inspection lot is created.

Can you give some brief material details and the date you have assgined for inspection plan?

If possible give me some more info.