Dear All
I Created the project my planned total for project is 100/-.I alloctaed a budget for 80/-.In customising in budget profile activation type is 0.In tolerance limit Availability control action is 3 i,e,, error message and usage is 90%.When i am proceesing PO for particular project i am not getting any error message since i am exceeding my budget value.Kindly help me regarding this issue
Regards&Thanks
P.Srinivasan
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check the following:
1. Possibly before activating availability control, you have incurred some actual costs greater than budget. Check in CJE0 report if there are any actuals costs.
2. Is your project definition level budget equal to or greater than below WBS elements' budget. Sometimes we tend to enter budget for wbs but dont enter/sum up for Proj Defn level.
3. If you have made changes in Budget profile, they dont get dynamically updated in Project. You need to reconstruct availabilty control for the Project. TC: CJBN
Hope this helps. Reward points if suitable.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
My doubt is what configuration i have to do for getiing a error message wen i am exceeding budgeting.I did configuration in tolerance limit in availabilty control as error option but i am not getting any msg during PO processing.Kindly guide me how i have to proceed further
Regards
P.Srinivasan
Hi
The configuration settings u ve to do are:
1. In the budget profile, in availability control put 1.
2. Untick all the other check boxes there.
3. Go to Define Tolerance Limits: & make the settings for the budg profile.
4. Now go to TCode CJEN: Enter the project no & execute.
go to TCode CJBN: Enter the project no & execute.
go to TCode CJEN: Enter the project no & execute.
This has to be performed & I am sure you ll get required results.
Plese revert back for any clarifications.
Regards
Sunil
Hi,
After assigning Budget, please check availability control of Budget. You can use transaction CJBV for activating Budget availability control.
Hope this will help you.
Best Regards,
Rakesh Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I activated the availabilty control indicator as 1.When i am allocating the budget at the time itself it is saying budget is exceeded.But before i activated the availabilty control indicater i allocated a budget for three projects. Kindly guide me how i have to proceed further
Thanks&Regards
P.Srinivasan
Hi,
If the availability indicator is 1 then during Budget allocation it will check availability control. There are 2-steps for Budget allocation to Project say original Budget & Budget release. Where exactly you face the errors ?
I think the Budget had n't allocated properly. Follow the budget sequence steps & hope you won't get any error. In case of any query,revert back with detail process.
Regards,
Rakesh
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.