Difference B/W End to End Implementation and Full life Cycle Implementation

Hi Experts

Can any one clarify me -what is Difference B/W End to End Implementation and Full life Cycle Implementation in BI

Thanks in Advance

Omkar

Former Member
Former Member replied

hi..welcome to sdn...

SAP follows ASAP methodology to make the project implementation.

a)Project Preparation

b)Blue-print

c)Realization / Fit-gap analysis

d)Pre-producton

e)Go-live / Production

Generally in project preparation top management / PM will discuss with the client regarding the business integration n pros n cons of implementation.

Blue print contains all the functional specs related to the project.

Realization is the place where u actually implement and provide solutions , like activation of Business content objects etc.

Pre-production is the place where u will test the project .

Go-live means actual production and u will support the issues hereafter.

Normally u will involve in the realization phase .

this thread will be useful for u:

clarify these

When u r working on the bw implementation depends upon u r experience task will be assigned to you.

Generally any sap implementation have same phases above what kalyan mention but it will vary from client to client.

Before going to u r task u need to understand the application(business process) of u r client according to that u need to configure or create or activate the objects.

once these objects completed in the development server u need to transport into quality server then u need to send into production server there u need to check whether objects r working according to u r client requirement.

Entire process will take some more time

Full Life Cycle - It has the scope, requirement analysis, coding/development, testing, go-live... Full life cycle of a project...

End-to-End Implementation - We will take an example that we want to implement the entire NetWeaver 2004s... From extraction to reporting to broadcasting etc.,

end to end impl:

1. AS IS process

2. To be process mapping

3. customizaiton in SAP + devepment

4. Unit testing

5. Full testing

6. End-user training

7. Go-live

8. Support for initial month-ends.

9. Ongoing support

End to End Implementation (SAP Life Cycle)

full impl:

1 Project Preparation / Requirement Gathering

2 Business Blueprint

3 Realization

4 Final Preparation

5 GO Live & Support

BW Implementation

Below steps are the the high level plan for the BW implementation

If it is End to End Implementation Project , You will be involved in all Phases

1. AS IS process - Study of the existing process.

2. To do process mapping - What will be the new process.

3. customizaiton in SAP & query development - Customizing the cubes and ODS,Reports

4. Unit testing - Testing of each and every module and reports

5. Full testing - Full system testing. In this step all steps are integrated so, it is also known as Integration testing.

6. End-user training - Training for the Power user (first line users) by the SAP Consultants. They will in turn train to other users.

7. Go-live

8. Support for initial month-ends. -

9. Post implementation support....

Full Life cycle

1.Project Prepararion

2. Blue Print

3. Project Preparation

4. Final Preparation

5. Go live & Support

check if this helps

Multi-Dimensional Modeling with SAP NetWeaver BI

https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/6ce7b0a4-0b01-0010-52ac-a6e813c35a84

Modeling the Data Warehouse Layer with BI

https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3668618d-0c01-0010-1ab5-aa75c3a4dfc2

Frontend Design Guidelines - SAP BI in SAP NetWeaver 2004s

https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/58fd9183-0e01-0010-f183-fdc9019f77ab

Enterprise Reporting, Query, and Analysis - Developers Guide

https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/0901c9bb-0601-0010-49ab-c1770c527673

check

https://www.sdn.sap.com/irj/sdn/developerareas/bi

'key topics'

check all Dr. Bjarne Berg's presentations on BW Project

http://csc-studentweb.lrc.edu/swp/Berg/BB_index_main.htm

http://csc-

e.g

studentweb.lrc.edu/swp/Berg/articles/PM05_Berg_Redmon_Scope.ppt

Managing a global BW project

http://csc-studentweb.lrc.edu/swp/Berg/articles/Global_BW_Rollout_v3.ppt

...

http://csc-studentweb.lrc.edu/swp/Berg/articles/Portals%202004%20-%20Managing%20BW%20project%20v5.ppt

How to Manage a BW project

http://csc-studentweb.lrc.edu/swp/Berg/articles/Managing%20BW%20project%20v3.ppt

hope this helps..

1 View this answer in context

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question