Dear all,
Exploring for the alternate material and their behaviour in APO, Got Some quries..
Are alternate material are cifed as a interchangeble component i.e. planning package in product master.
In interchangebility is there any limit for supersession chain products?
in one chain there are 4 parts e.g. A-> B ->C->D in where A and D are having MRP Type X0 while B and C are PD will demand flow to D as B And C are PD.
Regards,
Amol chavan
Interchangability is not CIFed from R/3. In your special scenario, Demand on A will not get propagated to D.
-Shibu
Thanks for rewarding points if this is helpful