Managers are having to change the required on date, because the leadtime coming from a catalog, is being added to the date the shopping cart is created. If the manager does not approve the car the same day. The system forces a change to the required on date before allowing manager approval. Managers don't like it. Any solutions?
Hi Michael,
You can change the error message to warning and then system will allow the manager to approve the cart even if the preferred delivery date is in past.
change the message from E to W through the path.
srm server -> cross application setting -> message control -> influence message control.
Cheers
Iftekhar Alam
PS : Please reward point for useful answer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can change the "required on" date once the SC is created for the items coming from the catalog using the BADI "BBP_DOC_CHANGE_BADI".
BR,
Disha.
Pls reward points for useful answers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.