on 08-02-2007 4:42 PM
Hi
Can any one guide me how to setup new plants in SRM, The plants are setup in back end and assigned to Purchase organization and company code.
Best Regards
sairam.
Hi,
You have to run reports
BBP_LOCATIONS_GET_SELECTED or
BBP_LOCATIONS_GET_ALL
Then goto PPOMA_BBP and navigate to extended attribute tab where you will have to select first your backend logical system and then your plants (= srm location)
Kind regards,
Yann
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Yann,
Thanks for your qucik reply,
I simply have setup plants in my backend and assigned them to company code and Purchasing Org. Other than that I have not done any thing on my backend.
However while executing this report BBP_LOCATIONS_GET_SELECTED , I m getting an error.saying that below mentioned.
Program Terminated with Errors
Check the Application Log BBP_LOCATIONS_GET
for Relevant Messages (Transaction SLG1)
But when I got to SLG1 it gives me all the list of plants plants which are existing since long excepting my new plants.
Please suggest.
Best Regards,
Sairam.