Hi,
When I create a scheduling agreement (Category : HG) say 31st bucket it automatically gets shifted to next bucket ( Weekly Bucket) Creating the scheduling agreement within the planned delivery time. Pls let me know the reason for this.
Thanks,
Siva.
Check OSS Notes 770315 and 757870.
There was a code issue for SNP Purchase Reqs which is corrected by notes 989857, 1045636 ad 1045891.
Also note that the normal process for Procurement Proposal creation is a Backward and then Forward Scheduling. Due to varying calendars (receving and shipping) at the locations the results of Backward and then Forward Scheduling can give differences. However it should not create the receipts late (as is your case).
Thanks,
Somnath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.