Date Problem in Scheduling Agreement Creation

Former Member
0 Kudos

Hi,

When I create a scheduling agreement (Category : HG) say 31st bucket it automatically gets shifted to next bucket ( Weekly Bucket) Creating the scheduling agreement within the planned delivery time. Pls let me know the reason for this.

Thanks,

Siva.

Accepted Solutions (0)

Answers (1)

Answers (1)

somnath_manna
Active Contributor
0 Kudos

Check OSS Notes 770315 and 757870.

There was a code issue for SNP Purchase Reqs which is corrected by notes 989857, 1045636 ad 1045891.

Also note that the normal process for Procurement Proposal creation is a Backward and then Forward Scheduling. Due to varying calendars (receving and shipping) at the locations the results of Backward and then Forward Scheduling can give differences. However it should not create the receipts late (as is your case).

Thanks,

Somnath