How to transport activities?

Former Member
0 Kudos

Hi all,

we need to transport activities in DP. Where can I do this?

We have APO release 4.1

Thanks for your help

BR

Jens

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Jens,

If you have this activities assigned in some mass process jobs, then you can transport this jobs.

1.- Go to Tcode /SAPAPO/MSDP_ADMIN

2.- Double click on your planning area

3.- From the menu select Goto->Transport Connection

4.- In Transport Jobs section mark the checkbox Transport Jobs and then select the jobs that you want to transport. All the activities that are assigned to these jobs will be transported.

I hope this can help you.

Regards.

Marín.

I'm really sorry. This functionality is available only for SCM 5.0

Message was edited by:

Ulises Marí

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Marín,

Is this option available in SCM 4.0. If so let me know how can I transport it?

Thanks,

SIva.

Former Member
0 Kudos

Hi Jens,

U can't transport the activity directly.

So find the master table for activity ( I hope /SAPAPO/TSPLBAKT is the one). Now pass the activity name there and select the record. Now on menu click (Table Entry -> Transport Entries) and it will ask u the transport request.

Regards,

Siva.

Former Member
0 Kudos

Hi Jens....i guess activities cannot be transported...u need to manually create it in all systems