on 07-31-2007 11:57 AM
Hi
when i create ro delivery does not take place ?why
Thanks
hema
hi
when an order is created as RO then a delivery document number is created but it dosent mean that delivery process is completed...
the delivery is done only by means of manul PGI process.. so go to VL02N and complete the PGI process..
if delivery document numebr itself is not getting created when RO is saved then chk ur document configuration....
In VOV8, select rush order and mark "Immediate Delivery" field as "X". Delivery will be created automatically
Reward if Useful
thanx & regards...
Naren..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
For Rush Order & Cash Sales you have to assign Shipping condition as 10, since in this both the cases delievry document is created immediately.
use the T.code: OVL2 and then assign shipping condition as 10 for your plant and shipping point.
Hope this will help.
Reward if it helps
Regards
Prasanna R
Hi
Rush Order Process:
1. Create Sales order, when you save the sales order, delivery document will be created.
2. Go to Change Delivery - VL02N and enter the delivery document no. and then do PGI.
3. Create billing document.
Reward if it helps.
Regards
Prasanna R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.