Hi Experts!

Does anyone of you know why in ChaRM CR Correction document the status of the document (controlled with Actions) switches back to "created" from status "In development". This switch happened to me several times when handling a normal correction and I don't know why it does that.

Usually I have done Action related task to the correction prior the status is swithced.

I've tried to look for a solution in the forum and in help docs but I haven't come accross any. Please don't get me wrong, I do get the full maintenance cycle working for normal corrections. This status change is more of an annoyance than an error.

We are using SolMan 4.0 SP09

Thankful for all hints I can get!

BR

Auli

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I found a previous discussion from this forum with Avinash's advice to use note 919477. This is exactly what I was looking for.

I'm recording it here just in case anyone ever needs to solve this in the future.