on 07-28-2007 10:59 AM
Dear Gurus,
I want to know that what are the basic configration of MTO scenario and if we are goin to make the sales order so the purchase order is goin to made automatically in the schedule line or the planned order is goin to made automatically in schedule line of the order.
Please i really need help
Immediate response will be rewarded.
Thanks,
Mohsin
Hi Vishal,
Make-to-Order (Customer Requirements)
Creating a Sales Order
Checking Requirements Using MRP
Requirements Planning
Converting the Planned Order into a Production Order
Confirming the Production Order
Checking the Settlement of the Production Order
Creating a Delivery
Creating a Billing Document
Checking Costs and Revenues on the Sales Order
Make-To-Stock Production
Planning a Product
Creating a Sales Order
Executing Multi-Level Requirements Planning
Converting the Planned Order into a Production Order
Withdrawing the Material for the Production Order
Confirming the Production Order
Creating a Delivery
Creating a Billing Document
REFER BELOW
Make-to-order processing takes place when inventory is not generally stoked but instead the firm wants until an order hass been placed and then produces just what has been ordered.
Ex: In this case, a deluxe motorcycle gas tank that must be produced form an unpainted tank, paint and gas cap. These are two processes that must be completed in the production -
paint the tank and when tank is dry, attach the gas cap.
The BOM are needed to create a given product. The routing information gives what processes need to be carried out in what order and even how long each process should take. All this information together can be used to determine what the total cost of the product and determining the profitability of the product.
ACreation of materials:---
T code: MM01
Ex; 1400-71xx
Enter material, ind. Sector and material type.
Select the org. levels plant, stor. Location, sales org, DC, Warehoused no, storage type.
Repeat the same process for all components.
BCreation of BOM:--
T code: CS01
CSet up routing:--
T code: CA02
Dpricing conditions:--
T code: VK11
Epurchasing materials:--
Create a purchasing order req. for components from vendor.
Create PO: ME21
FReceiving materials:--
GR:- MIGO
Go through MMBE then u will get stock available or not.
Process:
1. creating a sales order for product not kept in the inventory. This will atomically generated the relevant production order.
2. we assume production is done ahead of \schedule. After production is completed you will confirm production order as fully completed .
3. Newly determine the availability of sales order.
4. shipment
5. TO for delivery
6. Billing
7. Payments
Reward points if it helpful.
Regards,
Govind.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
if it is production with BOM, then planned order , production order,then goods posting to sales order stock., then delivery
if it is assembly order(i.e already goods manufactred it is the directly production order, no planned order)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks alot buddi.....over here its the assembly order......now for eg. i make the sales order,so how the production guys will know about the requirments and the production order will be created automatically or we have to create it after receiving the sales order......???
Please explain....
I appreciate it......
Thanks
Mohsin
Dear Mohsin
I know that requirements are passed on by Sales to Production by Transfer of requirement. This requirement can be seen in MD04 by PP
the settings are as following
Transfer of Requirements
Define Requirements Classes OVZG
Define Requirements Types OVZH
Determination Of Requirement Types Using Transaction OVZI
Define Procedure For Each Schedule Line Category OVZ8
Block Quantity Confirmation In Delivery Blocks OVZ7
Maintain Requirements For Transfer Of Requirements OVB8
Maintain Requirements For Purchase And Assembly Orders OVB5
Following has to be noted.
Item Category(from Sales Order) + MRP Type will determine Requirement type OVZI
then this Requirement type are assigned to Requirement Class OVZH
then if you see your requirement Class in OVZG
for e.g.
settings you can check by double click
200 Assembly: plnd order, where assembly type is 4
201 Assembly: prod.order, where assembly type is 2, with production order type given.
I hope this will be helpful,
Regards
Jitesh
Mohsin,
The settings at Schedule line level are just for fine tuning. They have to be set ON at requirements class level and can be switched OFF at schedule line level.
The procurement type and the strategy group in the MRP views are also important. These are set by the PP consultants.
Thanks
Vishal
Usually for Make-to-Order, PO is not required but a production order is generated. For this to happen automatically, you have to configure the schedule line categories correctly.
Regards,
Noufel P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dera Mohsin,
Building Block Guide for MTO:
http://help.sap.com/bp_bblibrary/500/html/J66_MTOQPOP_EN_IN.htm
Building Block Guide for MTS:
http://help.sap.com/bp_bblibrary/500/html/E34_MTSExtProc_EN_IN.htm
PO will be made automatically in schedule line of the order.
Regards,
Naveen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.