While running the EOQ and SFT planning service, we get the following error
"No valid transportation lane between Supplier and LOC1". LOC1 is the entry location for our BOD.
We have not created any procurement relationships as we are working on a standalone SCM trialbox.
Appreciate any help/suggestions to resolve this issue.
Thanks & Best Regds
Mitesh
You have to create a contract or scheduling agreement (info record is not suitable).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Somnath and Mikalai for your help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mitesh,
You need to have valid transportation lanes from the supplier. Maintain it manually. If I remember correctly it is possible to have External Procurement Relationships in APO only (type 4) and not just contracts, purchasing inforecords or scheduling agreements CIFed from ECC.
Hope this helps.
Thanks,
Somnath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.