DEAR GURUS,
HOW TO MAKE USE OF THIS T_CODE (CCUNDO). I AM NOT ABLE TO MAKE OUT WHAT THIS DOES. I HAVE TRIED CREATING CHANGE NOS. THEN CHANGING THE ATTACHED OBJECTS USING THE CHANGE NO.
LATER I TRIED TO UNDO THE CHANGES USING THIS T_CODE.. BUT IT ALWAYS GIVES THE MSG. "No changes found for change number ".
I AM USING ECC6.0.. THIS T_CODE WAS NOT AVAILABLE IN 4.6C
CAN ANYONE HELP?
Hi Abhishek,
this undo functionality works for the following objects:
- Bill of material
- material master (planned changes only)
- Variant configuration objects (object dependencies, configuration profile, variant table)
There is a BADI ECM_UNDO to extend support for additional (customer) objects or enhance the standard behaviour.
Please reward points if answer is helpful.
Best regards, Daniel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Daniel
I was looking up on CCUNDO and not able to find a way to activate it. I could only find this thread on Google search.
When you mention "Material Master - Planned changes only" what does it mean? How is a change planned to the material master, by what means/transaction? does this mean that we can not use this transaction CCUNDO to reverse a change done through MM01, with ref to an ECN?
Please let me know if you know what purpose it works. Thanks a lot for your help.
-Ram
+1 (972) 999 0420
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.