hi all,

I have a problem with bom. Myclient has following the bom sales. which is maintained price at Main Item level, components are not relavent for pricing.

Now i want to give the header discount for Bom order and that amount should distribut among Components with respective to their costs which is maintained at material master record.. which calculation type i have to maintain for header condition types.\

pls help me.

thanks for all.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Try copying from Condition Type HA00 or HB00. one of them should work as per your requirement.

Regards,

Rajesh Banka

Reward points if helpful.