In PI Sheet ,no Coproducts will be shown

Former Member
0 Kudos

Hello Specialists,

In my current project, the customer want to use co.products, which work fine from the controlling point of view, but in Process management, we are using HTML based PI Sheets. The PI Sheets are not showing the Materials, marked as Co product. I´m using the message type PI_Cons, but I assume that this type might be the wrong one.

Hope you can help.

Regards. Alex

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

PI_CONS will only show you the list of materials that are to be consumed against a Process Order, but the Co-Products will be an output with the main output.

So the Co-Products are not displayed in the above message.

If you want to post a goods receipt for the header material of the order or for a co-product, you need to send a message of category PI_PROD to destination PI03.

Answers (0)