on 07-24-2007 3:37 PM
Dear all,
We are using WBS elements to monitor budget and then maintenance orders to manage work execution. Budget is then assigned to the WBS structure and the availability control is done at the last WBS level.
My point is about the calculation of assigned values which are displayed in the S_ALR_87013558 report. They are not the same when looking at the last level of WBSE and at the maintenance order level.
For order: is taken into account PR and PO values
For WBS: is taken into account only <b>PR</b> values
The correct value is at order level.
We found out an OSS note giving a solution (307294) but it is not relevant for our SAP release (47).
Is there any way to correct this calculation method?
Thanks in advance for your help!
Warm regards,
Laurence
No idea about the relevancy of this SAP behavior?
Thanks in advance,
LA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Laurence,
May I suggest you to review note 178837?
You will find useful information there on how the Assigned value is calculated and correction instructions in case it is inconsistent.
Hope this helps
Regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check the account assignment for PO. It should display wbs element in order to update the costs.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.