i have 1 doubt...suppose when we give hrozon for 2months in dynamic chek,,,if we want to take in to consideration of open doucmnets..after 2months then how...,

do we again have to increase the duration.period..?

regards

vivek

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi,

the system takes all the open orders within the horizon period , if u want to take after the horizon extend the horizon period that is the option,

also is that for all the customers or to a specific customer, if it is specific go for a

different risk category and a different check for him.

regards

reward points

sriram

Former Member
0 Kudos

Hi

The start and end dates define the duration of the billing plan. If possible, they are taken from the contract data. You may decide "not" to set an end date (if the duration is unlimited). In this case, new dates can be extended to the horizon (the horizon specifies the number of settlement periods that are set in the billing plan).

so only based on the above, you decide if or not you want to increase the duration