on 07-22-2007 6:38 AM
sd gurs
i have 1 doubt...suppose when we give hrozon for 2months in dynamic chek,,,if we want to take in to consideration of open doucmnets..after 2months then how...,
do we again have to increase the duration.period..?
regards
vivek
hi,
the system takes all the open orders within the horizon period , if u want to take after the horizon extend the horizon period that is the option,
also is that for all the customers or to a specific customer, if it is specific go for a
different risk category and a different check for him.
regards
reward points
sriram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The start and end dates define the duration of the billing plan. If possible, they are taken from the contract data. You may decide "not" to set an end date (if the duration is unlimited). In this case, new dates can be extended to the horizon (the horizon specifies the number of settlement periods that are set in the billing plan).
so only based on the above, you decide if or not you want to increase the duration
HTH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.