Hi All,
We have one transport target group /DEVALL/ .Which we deleted and created two target group for importing into different client as /DEV100/ and /DEV200/.
Now alll transport request which has been assigned to /DEVALL/ are coming as a local request and after released they were not going to import in any of the client.
Please let us know the way by which we can assign new target group (/DEV100/ and /DEV200/) to all these change requests (TR's).
As we can manually assign target to change request at the time of import.But we want to find out the way of assign target group before releasing the TR's
Thanks in advance for your valuable and fast response.
Hi Sumit,
I am only aware of making this change using transaction se09 and se10. You select the change request number 'Not the task' by double clicking on it. In the resulting screen, select the properties tab. The 'Target' field in the screen can be used to perform the reassignment.
Sajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.