When a material is assigned to a network activity in the project and
the reservation is done for the WBS element, then the COST REL
indicator becomes disabled. As a result,the activity planned cost from
the material assignment to activity does not come.However the same
thing does not happen when the material is reserved for the Network.
The Project profile has got Non Valuated stock indicator as that is the
requirement.
Regards,
Himadri Tarafder
Hi,
Case 1: Reservation for wbs
Plan cost does not get updated when you are maintaining non valuated stock. When you select Non-valuated stock system makes material irrelevant for costing (removes cost relevancy tick).
This happens because material procured under this category will be received in Project stock, whcih you have defined non valuated.
Case 2: Reservation for network
In this case, material will be received in plant stock (which you have not defined non valuated). Thus system allows you to edit the cost relevancy indicator.
Reward points if helpful.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.