on 07-19-2007 3:31 PM
Hi Guys
I am facing an issue with Credit Management..The Problem is while
creating Maintenance Contracts it doesn't seem to be looking at the
available credit and it is stopping the contract from further processing
even there is sufficient credit available to the customer..So we have
to go to T-code VKM1 each time we create a contract and release the
contract manually. .However if we use the same customer for creating a
Standard Order credit limit works fine..
Can anybody help me in identifying the cause of this issue...
Regards
Prasad
Hi,
Check the item category WVN for Maintenance Contract item, in business data tab credit active will not be checked.
Check this out.
reward points.
chan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chan
I did check the 'credit active' field for the corresponding item category..We wanted the system to check the customer's credit limit every time we create a contract.But the Problem we are facing is Contract is blocked every time when it is created even there is sufficient credit available for the customer.
Regards
Prasad
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.