Hi,

can anyone tell me how should be completed a general value contract?

Thanks!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

To create a value contract, proceed as follows:

In the initial screen, choose Logistics ® Sales and distribution ® Sales.

Choose Contract ® Create.

In the Contract type field, choose Value contract, and enter the required organizational data.

The values for sales organization, for distribution channel and the division are usually proposed from user-defined parameters. Entries for the sales office and the sales group are optional.

In the standard system, the following two sales document types are defined:

– Value contract general (VC1)

– Value contract general (VC2)

Choose Enter.

Enter the following data:

– Customer number of the sold-to party in the Sold-to party field.

– Customer purchase order number for this document

– Validity period in the Valid from and Valid to fields

– Description of value contract

– The master contract number (see also Master Contracts)

– Material number(s)

– Target values for the materials

The target value is the planned entire value for the material in the contract.

– only for value contracts not referring to material: Product hierarchy and/or assortment modules

Additionally, you can define contract duration for the value contracts VC2 in the Contract start date and Contract end date fields. You can define both contract duration and header level per item. The contract duration at item level can be different to the contact data at header level.

Choose Enter.

If you want to enter further data for the header or items, select the corresponding menu entry. If you wish to change data for an item, select the item before you choose the menu entry.

Enter all the necessary data.

Save the document.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

My question was how to get completed a value contract.

I've created the contract and released orders related to contract, the released sales value reached contract value but status of contract is still open.

pts if your answer helps

Former Member
0 Kudos

hi

in the configuration of item category in vov7 for wkn

Former Member
0 Kudos

in the item category VOV7 in wkn

select the completion rule as "e"

regards

prashanth