IDoc Control Record

Former Member
0 Kudos

Hi,

I have the following scenario:

R3a to XIa to XIb to R3b.

The communication from XIa to XIb is happening over a HTTP connection. When an IDoc is sent from XIa to XIb, I assume the IDoc control record is modified for the sender port and RFC destination when we do the configuration of in IR/ID?

Accepted Solutions (0)

Answers (1)

Answers (1)

moorthy
Active Contributor
0 Kudos

Hi,

<i> I assume the IDoc control record is modified for the sender port and RFC destination when we do the configuration of in IR/ID?</i>

>>>Yes it supposed to be..Hope you are not doing any Header mapping etc in the XIb. IF not, it should pick the Control Record info from SLD as per the Technical System and Business system. Hope my understanding of the question is right here.