Whether to use new SNP Planning Area

srinivas_krishnamoorthy
Active Contributor
0 Kudos

Hi

We have a new business line that we intend to go live with in SNP that will have entirely different kind of Unit of Measures though there will be conversions maintained with respect to the current Unit of Measure of SNP Planning Area. We are contemplating going in for a new SNP Planning Area. Would anyone know on whether there are any more guiding factors to go for a new SNP Planning Area? Are there any negative consequences in going for a new SNP Planning Area?

Thanks

Srinivas

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi..

You can create New SNP planning area,

While creating New planning Area, Ensure that you are copying planning object structure properly and modifying it, Copying the aggreates

All related Macros...

If you are taking care of it there is no harm to create new SNP Planning area.

For future is SAP is doing any change for standard planning area then you will require to take corrective action for the upgrade.

Hope you got some input!!!