on 07-17-2007 7:12 AM
Hi,
We update time stream (planning calendar) in the configuration by
generate the period for year 2008 (Our current planning calendar is
until 01.01.2008 only) in the development server.
But when we come to the Product Planning Table(PPT), the
particular columns after 08.01.2008 are grey off. (meaning we cannot
key in any orders for those columns/shift). We already try to change
the active variant for the capacity, save and then change it
back to what it was for the affected resource, but it is still not
working.
Kindly pls advise. Thank you.
Hi Sim,
Can you please update how the changes got reflected in PPT. We are also facing the same issue where the factory calendars and the planning calendars have been updated, but this is not reflecting in PPT.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.