Hi All,
While doing UAT testing For Construction in Progress (Asset Accounting) (t.Codes AIAB & AIBU) for settlement, I received an error "Define a number range for settlement Documents". Can anyone please help me to solve this error. Where should I define number range for setllement documents?
Thanks & Regards
I did a reseach on this and came up with a solution all by myself.
Wanted to share this will other users.
Solution -
Use Transaction Code - SNUM and activate the group under the required controlling area. This will allow us to define a number range for settlement documents for Internal Orders.