Hello,

I have read in a forum on SDN about the following behaviour of Change Request Management in case of a Maintenance Project: after completing import to production environment through Normal correction, when the same maintenance cycle

is used again, ChaRM reimports all the TP's imported in the previous run.

In case of an Implementation Project with Normal correction I guess that this can not happen for an import to Production environment, because it's not possible to use again the same cycle, is it right?

But if we consider the import to Test environment: for example, during a Project cycle, transport request TR1 is imported to Test environment, then cycle status is set again

to "In development" and a new transport request TR2 is created. Is TR1 re-imported, when TR2 is imported to Test?

Thansk a lot,

Stefano

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Whenyou import a normal correction as per the recommedations from SAP they are asking to de select keep for further imports options,so that when we import other request it will not import the older request.

Please revert for any clarifiaction,

Thanks and Regards,

Avinash.