Former Member
0 Kudos

While creating rush order the following error is see how to overcome this,kindly help me

shipping condition 10 loading group 0003 plant ausp storage loc ausl not defined:

thamks

cheers

hema

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Go to T.Code: OVL2 and maintian the combination Shipping condition, loading group, plant with the shipping point.

In your case

10 + 0003 + AUSP = AUSL

Regards

AK

Reward points if helpful

Answers (5)

Answers (5)

Former Member
0 Kudos

By useing the t-code---->OVL2 you can fix the problem

SC--->10

LGRP--->0003

PLANT---->

SHIPPIN POINT---->

assing the your plant and shipping ponit

Former Member
0 Kudos

hi Hemavaty

pls check your Shipping point determination configuration. pls maintain for your requirement and see that storage loc ausl exists in the plant ausp

reward points if helpful

Jai

Former Member
0 Kudos

HI Murali,

Check the Shipping point determination. also check the assignment between Plant and Shipping point.

Reward if it helps

Regards

Srini

Former Member
0 Kudos

Hi pls check with the shipping conditions in customer master and loading group in material master

Other wise <b>OVL2 </b> T-code

spro>LE>shipping _--basic shipping functions _assign shipping points

here u need to assign loading group shiping conditionsplant +shipping point

Message was edited by:

SHESAGIRI GEDILA

Former Member
0 Kudos

hi,

go and do the shipping point determination

use the transaction code OVL2

give your shipping condition=01, loading group=003,PLANT=ausl, give your shipping point

pls reward points if the answer is helpful

Regards,

Murali