on 07-13-2007 11:17 AM
Hi all,
in APO release 4.1, we face the following problem.
In a process chain for DP background processing a material with historical data can not be forecasted and the log states the following error message: "Not possible to carry out the forecast - no historical data" ("Message no. /SAPAPO/MA502")
Does anyone know why we get these error message?
Thanks in advance
Tobias
Dear Tobias ,
You probably have configured to extract the history for the forecasting from R/3 through BW .
Check for the execution of the job wherein the history is loaded from R/3 .
This message comes after background job for Demand Plan is executed as due to univariate forecasting tool applied there is no history available to prepare the forecast .
Regards ,
Prashant Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Tobias -
Are you uploading the historical data from a Flatfile or transferring it from R/3?
Are you able to view the data once it is loaded into an infocube?
Take a look at the assignment of historical keyfigure to the infocube in Planning area?
If you are assignments are there then look at your CVC combinations?
Also take a look at your planning book are you able to see the historical data that you uploaded populating there?
hope this helps
Regards,
Suresh Garg
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.